Current Projects
Civil Construction
Project Name : HAZRAT SHAH JALAL INTERNATIONAL AIRPORT 3RD TERMINAL EXTENSION PROJECT
Main-contractor : SAMSUNG C&T
Sub-contractor : JINSUNG
Sub-sub-contractor : B&F Engineering & Construction Ltd.
1. AGGREGATE STORAGE WALL CONSTRUCTION: CIVIL PART
We have completed aggregate storage civil work at RMC site in HSIA Extension Project. This construction includes:
-
Aggregate storage wall base casting
-
High rise wall (4.75m height) shuttering work
-
Concrete Casting



2. PAVEMENT CONSTRUCTION WORK
We have completed Concrete Pavement Construction work at RMC site in HSIA Extension Project. This construction work includes:
-
Soil Compaction and leveling work
-
Rebar Fabrication work
-
Concrete casting work of approx. 3200 Sqm area.

.jpg)
3. TRUCK SCALE CONSTRUCTION WORK
We have completed Truck Scale Construction Work at RMC site in HSIA Extension Project. This construction work includes
-
Soil Excavation & leveling work
-
Rebar Fabrication work
-
Concrete casting work.



4. Generator Room & Car Wash Construction work
We have completed Generator Room base Construction Work and Car Washer Construction work at RMC site in HSIA Extension Project. This construction work includes
-
Soil Bed preparation & leveling work
-
Rebar Fabrication work
-
Concrete casting work.

.jpg)

LABOR CAMP (ASHKONA) DRAINAGE CONSTRUCTION WORK:
RCC U-TYPE DRAIN & BOX CULVERT CONSTRUCTION
We are doing construction work of 400m U-Type (W-1m) RCC Drain and Box Culvert. This construction work includes
> Soil leveling work
> Rebar Fabrication work
> Concrete casting work.